top of page

Dual Softener for Cooling Tower Makeup Water at Chemical Plant

Customer Needs

 

The client is a global chemicals manufacturer, with a manufacturing facility built in Richmond, focusing on adhesive production. Their cooling tower was tested with high hardness in water, causing all the downstream heat exchangers to scaled and


Our Delivery

 

Together with NAPE, we have successfully delivered a 6,500 L/h water treatment system

  • 5μm Filter

  • Activated Carbon + Quartz Sand Filter

  • Dual Softener


The dual softener is designed to operate 24/7 without any downtime in backflush and regeneration cycle to accomodate the continuous plant operation.


System Outcome

 

  • Total Free Chlorine : < 0.1 ppm

  • Total Free Chloride : < 0.1 ppm

  • Total Hardness : < 1.0 ppm




Location

Richmond

Capacity

6500 L/hr

Application

Cooling Tower Make-up Water Softening